Home
My Wrekin
Severn Trent Earl Shilton Treatment Works

Earl Shilton Treatment Works

  • Severn Trent

  • Earl Shilton Sewage Treatment Works

​​​​​​Wrekin Products was approached by Severn Trent’s contractor to discuss the creation of site access and a proposed working platform to be installed at the sewage treatment works at Earl Shilton, south west of Leicester.

The works was being developed to increase its waste processing capacity. The proposed plant for the site works required temporary works access as well as a working platform for the concrete pump and hydraulic (Kobelco CKE700) crawler crane.

The traditional approach to working platform design is to use a BR470 design methodology as suggested by BRE – Working Platforms for Tracked Plant (2004). Instead, Wrekin’s technical team proposed using a form of load spread analysis incorporating the use of E’GRID Biaxial geogrid. This meant the working platform thickness could be reduced by a further 40% compared to BR470.

Although the application area was not large, when operating in such confined spaces, the benefit was significant. Reducing the resources required can have a very positive impact on such a restricted site, not only reducing costs, but also minimising the contractor’s construction programme and overheads.

Earl Shilton working platform

The value-engineered solution provided by Wrekin Products cut our costs by 40%. We were very pleased with the savings made, but also the technical support and the professional levels of service provided.

Sam Harris

MWH Global (Stantec)

Earl Shilton working platform

Within a well-managed time-frame, the technical team was able to value engineer the traditional approach to working platform construction. With tight site constraints and limited resources, the impact on value engineering the temporary working platform was a 40% cost reduction, after an allowance for the cost of the geogrids.

Throughout the project, Wrekin assisted with the coordination of the proposals, collaborating with the full supply chain, which included Noble Works as the scheme designers and Stantec as the Tier 1 contractor.

E’GRID Biaxial geogrid from Wrekin is a large aperture polypropylene geogrid used to reinforce the ballast layer, reducing ballast settlement and subsequent maintenance intervention following ballast renewal.

E’GRID delivers ground stabilisation under roads, railways (Wrekin Products has a Network Rail certificate of acceptance for E’Grid Biaxial Grid) and paved areas. Employed in single or multi layers, the tough platform created provides tremendous load dispersal, allowing previously weak soils to be reclaimed for a wide range of uses, including, as at Earl Shilton, for access roads and platforms.

When granular particles are compacted over E’GRID Biaxial grids, they partially penetrate and project through the apertures to create a strong and positive interlock. The load dispersal effect from the interlocking mechanism increases shearing resistance within the soil, improving compaction and allowing the sub-base thickness to be decreased, ultimately cutting construction costs and time.

Related case studies

Related case study

Supporting the Scottish National Gallery Revamp

The Scottish National Gallery in Edinburgh has been home to a hugely prestigious, multi-million-pound transformation project, Wrekin provided solutions to provide top soil erosion control.

AHF Construction Management
AHF Construction Management
Read more
Related case study

Longhill burn Wind Farm

A new multi-million-pound wind farm is currently being constructed in West Lothian and, upon completion in 2022, it will be one of the largest onshore farms in the UK. Work at Longhill Burn wind farm in West Calder started in April 2021, with operations and management delivered by leading wind farm business, Energiekontor UK.  

A E Yates
A E Yates
Read more