Home
My Wrekin
Hinkley Point C haul road using Wrekin geosynthetics

Hinkley Point C Nuclear Power Station haul road

  • EDF Energy

  • Hinkley, Point C

  • 10 km haul road

  • 100,000 sq m of materials supplied

J. Murphy & Sons and Balfour Beatty contacted us to help with the construction of a ten-kilometre haul road that would support the first UK nuclear power station to be built in over 20 years. 

When complete, Hinkley Point C in Somerset will provide low carbon electricity for around six million homes across the South West. However, the existing road network and infrastructure was insufficient to cope with the demands of the construction process.  

Wrekin was approached by contractors J. Murphy & Sons and Balfour Beatty to support the creation of a ten-kilometre haul road. This would allow construction traffic to drive directly into the sites where new pylons were being erected and underground cables installed.

Wrekin visited the site and discovered it had a high level of variability in soils, but for construction efficiency, a constant cross section to suit the differing ground conditions was needed.

Nuclear Power station being installed in Hinkley

Wrekin advised that a single compaction layer at 250mm with a geogrid would suffice. Without a geogrid value-engineered solution, the client would have needed to install a cross section in two compaction layers, totalling 550mm.

Shahid Raza

Wrekin Products Ltd.

Hinkley Point C Nuclear Power Station

The significant length of this access road would typically create a substantial drain on the resources required for installation. For this project, Wrekin advised that a single compaction layer at 250mm with a geogrid would suffice. Without a geogrid value-engineered solution, the client would have needed to install a cross section in two compaction layers, totalling 550mm.

For the installation, 100,000sq m of Wrekin products were used. SX 3030 was installed over a layer of its FasTrack™ 609 separation geotextile – both with a manufactured four and a half metre width to suit the subgrade interface. 

This substantial reduction in foundation thickness reduced cost and environmental impact while accelerating the construction process.

With the implementation of geogrids, the access road is now operational, enhancing site accessibility for the construction team while allowing onsite HGVs to bypass the local road network.

Through utilising Wrekin Products’ geogrids instead of traditional foundation methods, the temporary access road can be exhumed at a faster rate and significantly reduced cost once the project is complete.

Overall, this project provides a clear demonstration of value engineering that can be achieved through using geosynthetics.

Related case studies

Related case study

Whittington Rifle Ranges

The existing stop butts at Whittington Ranges had not been used for many years and had fallen into a state of disrepair. Our client was tasked with reinstating the stop butts and bringing them up to current safety standards so that the range could be re-opened for use by the armed forces.

Landmarc
Landmarc
Read more
Related case study

Helping Alan Titchmarsh to ‘Love Your Garden’

Wrekin Products, manufacturer of intelligent products for civil engineering, was selected to supply its Turf Mesh and Weedstoppa geotextiles to the ITV series ‘Love Your Garden with Alan Titchmarsh.’ The objective was to completely redesign the garden of Bolton resident Caroline Hall. Animal lover Caroline was an RSCPA Inspector until a spinal stroke left her with severe nerve damage. 

ITV
ITV
Read more