Home
My Wrekin
M25 London

M25 hard shoulder improvements

  • Mouchel

  • M25 Junction 8-9 N

  • Manhole cover

  • Unite

Mouchel were contacted by the Highways Agency (HA) and tasked with investigating the most cost effective and reliable way to utilise the hard shoulder of the M25 during peak rush hours. This posed several engineering problems, of which one was to consider the service life of the manhole covers that would now be located in the wheel track of one of Europe’s busiest stretches of motorway.

he engineers considered three possible options for both the covers and services beneath, in order of cost:

  1. Install covers that will provide long term performance in an extremely high intensity traffic location.
  2. Leave the services in place and install access shafts from the side of the carriageway.
  3. Move all existing services to a location away from the carriageway.
Unite E600

Product trials

In order to evaluate option 1. Mouchel carried out a trial installations using numerous BS EN 124  class E600 600 x 600 x 150mm units from a wide selection of UK manufacturers & suppliers. The choice of E600 units was driven by a directive from the HA to use E600 in heavy traffic locations. The theory being that E600 units would be more durable.

The ever increasing instances of failing D400 manhole covers throughout the UK road network is well documented, as a direct result of this it is now common practice to specify E600 rated covers rather than D400 in high intensity highways (above class 4).

Wrekin were requested by Mouchel to supply a product for the trial being conducted on the M25 between junctions 8 & 9 northbound, to be tested alongside the other available E600 products. Wrekin were the only manufacturer to supply a D400 product, this being our Unite design.

Wrekin have invested heavily in researching the mechanisms leading to premature manhole cover failure. This is conducted using FEA analysis, supported by verification from various test sites. The result is that Wrekin fundamentally understand the ‘modes of manhole cover failure’ in the carriageway. The culmination of this process is the Unite manhole cover concept, which brings together key design aspects.

The Unite design addresses the following principle failure mechanisms:

  • Cover deflection is limited, and overall design reduces the effect of movement on seating wear.
  • Dynamic traffic loads are transferred to the substructures reducing the distress on the support work.
  • Frame design mitigates against cracking of the surrounding road surface.

Test results

Images were taken of one of the previous E600 units which had failed after 3 weeks of service, these images clearly show that fractures to both the cover & frame had occurred. We conclude that the intense dynamic loads being transferred through cover to frame and then substructures have resulted in overbearing stresses within the manhole cover assembly, its design simply did not cope with these dynamic forces. The onset of such failures can be seen in the fracturing of both the bedding mortar and road surface around the cover & frame.

Under BS EN124:1994 manhole cover designs have only to pass static load testing, however this trial again highlights that the carriageway environment provides conditions of varying and intense dynamic loads. It is evident in this example that products designed to pass the static load tests do not provide the engineering qualities to withstand intense carriageway conditions.

At the time this case study was issued, the Unite assembly supplied was still performing and has to date not been replaced. (Last sighting 11.10.12)

Previously installed failed E600 manhole cover frame

Related case studies

Related case study

Ensuring a smooth commute between Northern Ireland’s biggest cities

The Department for Infrastructure in Northern Ireland committed to funding a £185m ‘flagship’ infrastructure project to upgrade the A6, with the aim of reducing congestion and improving road safety. Richard Stewart, Regional Director ‑ UK North & Ireland at Wrekin Products, explains how a combination of excellent service and just in time deliveries secured an exciting opportunity to supply Highway® manhole covers and gully grates to such a significant project.

Department for Infrastructure Graham Construction Farrans
Department for Infrastructure Graham Construction Farrans
Read more
Related case study

16 years later, our Piccadilly Circus story goes on

Piccadilly Circus is one of the busiest road junctions in Europe and an iconic part of London’s West End – what you may not know however is that it is also home to one of our original Unite access covers.

Thames Water
Thames Water
Read more