Access cover installation guide

Step 1 - Prepare

Ensure:

  • The clear area of the frame is the same or larger than the chamber opening.
  • The frame is aligned with the opening.
  • The top of the chamber is sufficiently rough to 'key' with the foundation mortar.
  • An area of at least 50mm all around the outside of the base of the frame at the chamber top opening is clean, dry and clear of any loose debris.
Installing highway image 1

Step 2 - Measure

Depth to the chamber from the base of the frame

  • ≥85mm = Lay another course of bricks or proprietary shaft section.
  • ≥30mm = Use Uniform adjustment units and mortar.
  • ≤30mm = Use Unipak mortar.

Step 3 - Installation

Any necessary adjustment units shall be placed on and interleaved with bedding mortar and tamped to the required level leaving room for the top layer of mortar.

Lay a top layer of mortar about 50mm wider than the frame in one even pass. If this is not achievable, then wedges should be used, and mortar packed under and around the frame by hand.

The final mortar course for setting the frame should be all one mix.

The finished sandwich of adjustment units and mortar with the frame on top can be tamped, but not the units themselves (as they will 'spring').

Step 4 - Bedding

Place the frame and fill any remaining under-frame gaps with bedding mortar.

Unipak installation instructions

Step 5 - Tamp

Gently tamp the frame into the mortar to align the top edge of the frame within 5mm of the expected finished surface level, wearing course or pavement.

Installing Highway image 5

Step 6 - Encapsulate

Add additional bedding mortar on top of the frame flange in order to completely envelope it to a minimum depth of 10mm.

Hand-pack this layer of mortar using suitable gloves until it completely merges with the mortar extruded around the frame and through any apertures in the frame flange.

Note:10mm is the minimum depth of UniPak™ mortar layer to be laid under and above the frame.

Installing highway image 6

Step 7 - Key

The final layer of Unipak bedding mortar should be compacted and NOT be trowelled smooth but should receive a brushed finish so that it has sufficient texture to ensure it will mechanically key to subsequent road-fill materials.

Note: If frame fixing anchors are to be used in conjunction with a bedding mortar, drilling or hole-forming to receive anchors should only occur when the bedding mortar has fully cured. Ensure any fixing location is appropriate to receive the fixings and expected loads. Our covers are not supplied with fixing anchors.

Installing Highway image 7

Step 8 - Seal

Before backfilling with proprietary road fill materials, heavily coat the outside face of the frame and the inside face of the road surface with a suitable bitumen-based cold joint sealer and ensure that the bedding mortar has cured

Note: The application of a cold joint sealer to the vertical face of the frame is particularly important if the frame is to be located in a concrete road or pavement.

Installing Highway image 7

Step 9 - Surface

Install the remaining road fill and wearing course/pavement materials. If using flowable materials such as concrete, form a barrier over hinge apertures to prevent ingress of surfacing. Take care not to disturb the frame, particularly where mechanical equipment is employed.

Note: Materials suitable for backfilling and road surface repair of the access cover or gully grating frame (already fixed in place with polyester resin mortar) should hold HAPAS/BBA approvals, where available

Installing Highway image 9

Step 10 - Complete

Apply overbanding to the join between the new surfacing material and the existing surface. It's important to cover any saw cuts that extend beyond the reinstated area in accordance with manufacturer's instructions.

Attention: Ensure that trafficking of the finished installation does not occur before the bedding mortar and surrounding surfacing materials have fully cured. Overbanding is applicable to bitumen-based road surfacing only, not concrete pavements or similar.

Installing Highway image 10

Step 11 - Protect

In situations where the final wearing course is to be installed at a later date, apply a ramp around the projecting frame to ensure public safety and protect the frame from impact.

Attention: Ensure that trafficking of the finished installation does not occur before the bedding mortar and surrounding materials have fully cured.