Home
My Wrekin
Ground stabilisation for Code Fitness Gym

Ground reinforcement for Code Fitness Gym

  • Code Fitness Gym

  • Newark, Nottinghamshire

  • Capping layer reduced by 350mm2

We successfully implemented a ground reinforcement solution for Caliber Construction to complete the development of Code Fitness Gym in Nottinghamshire.

After encountering ground problems during the construction of a new gym on a countryside business park, Caliber Construction knew who to contact. However, contacting us after works had begun meant the need to provide a time effective solution was critical.

Careful examination of the ground investigation report revealed that we needed to address inferior ground conditions on various elements of the site, including the new private access road, car park and safety perimeter surrounding the soon to be built building.

Our geosynthetics team immediately identified this and explored all options as a matter of urgency. Above all, the need to strengthen the ground was the primary concern agreed upon by both the contractor and ourselves.

Our proposal, initially containing a wide variety of potential products, was approved and our work soon commenced. However, we first needed to engage in an extra level of technical discussion to settle on the most suitable solution for the problem in front of us.

Code Fitness gym geogrid installation

Our solution reduced the layer of capping to 250mm and saved roughly one metre of ground removal, replacement, and aggregates installation.

Shahid Raza

Wrekin Products Ltd.

Code Fitness gym geogrid installation

We provided a cost-effective, recycled capping and SUD-based design, which fit perfectly before the final surface layer was placed on top. Unique areas, such as an area of permeable paving, were accounted for by using different aggregates where needed.

If not for our expertise, the one per cent CBR subgrade work would have included anything up to one metre of ground replacement, 600mm of capping, a SUD-based layer and upper surface layer. However, our solution reduced the layer of capping to 250mm and saved roughly one metre of ground removal, replacement, and aggregates installation.

As with all of our solutions offered, the contractors were pleased to make great time and cost saving while improving health and safety in the process. Furthermore, future environmental issues were mitigated during an important early stage of the development's lifecycle due to our forward thinking approach.

Gallery

Related case studies

Related case study

Whittington Rifle Ranges

The existing stop butts at Whittington Ranges had not been used for many years and had fallen into a state of disrepair. Our client was tasked with reinstating the stop butts and bringing them up to current safety standards so that the range could be re-opened for use by the armed forces.

Landmarc
Landmarc
Read more
Related case study

Ornamental Pond at Fallow Park

Fallow Park is an exclusive housing development on the outskirts of Cannock. A 1400m2 ornamental pond with green space was designed to enhance the development and provide a habitat for a variety of wildlife. The ground conditions and nature of the finished pond meant that an impermeable membrane would be required to line the pond.

Jessup Brothers
Jessup Brothers
Read more