Home
My Wrekin

Our Solutions

Embankments, Slopes, Bunds and Walls

What if contractors could construct embankments, slopes, bunds and walls during the construction phase by using more aesthetically-pleasing solutions and increase site usability?

Embankments, slopes, bunds and walls

Slopes and structures on projects commonly follow a shallow angle and are conventionally constructed from reinforced concrete. However, our aesthetically pleasing innovations ensure a reinforced steepened slope can increase the usable area on site, thereby increasing the value of the land available.

Plus, a reinforced soil slope, rather than concrete, is much more aesthetically pleasing for residents, particularly with a planted face. As well as being far more aspirational, a reinforced retaining wall will reduce costs and time on a construction programme, often by up to 50 per cent. These savings can be increased further through curved and tiered reinforced soil retaining walls.

Freeing up additional time

Reinforced concrete options for slopes and structures are labour intensive to install and carbon intensive to create. Our E’GRID Uniaxial geogrid solution can be invaluable in overcoming these issues and help to find additional time in the build programme – before the first on-site construction even begins.

As a result of innovation in the geogrid sector, a reinforced steepened slope can be engineered, increasing the usable area on site, thereby boosting the value of the land available.

Soil banks are constructed by wrapping the geogrid around the soil face to the required slope angle; this process is repeated in layers to create a stable/steep embankment.

These solutions offer a more sustainable option to the traditional concrete alternatives, and are also much more competitive on cost and can be constructed far more quickly. They also improve the bearing capacity and safety of a structure.

Further cost savings can be made by re-using on-site material, even from previously failed slopes, which can be excavated and re-used to construct a stable embankment or slope.

Reinforced slope

Embankments, slopes, bunds and walls in numbers

Wrekin geosynthetic solutions have been used on thousands of projects to provide significant costs savings as well as promote sustainability and reduce emissions.

reductions available on construction programme.
50%
cost reductions available when using E'GRID.
40%
MultiTrack supplied 2016-2021.
>50million m²
Working side by side

A supportive team

We have developed a strong reputation in the civil engineering sector thanks to our skilled teams wealth of experience. We offer the best technical expertise with exceptional customer support. Our team works with asset owners, developers, main contractors, ground workers and local authorities throughout a construction scheme’s lifecycle, including:

Initial project support

Listening and working with customers to fully understand their requirements. We provide pre-tender and tender support to lend a competitive edge.

Product specification

Our technical experts and value engineering service means that you have access to the best advice and support.

Design schemes

Our talented team provides full design services, with the added bonus of supporting documentation and drawings.

Advice and site meetings

We understand the value of regular site meetings, helping to improve communication, giving installation advice and ensuring each project is completed successfully, right down to the project review

Old Colwyn embankment
Success stories

Old Colwyn embankment repairs

We were approached by Alun Griffiths (Contractors) Limited, and Atkins to advise on a suitable geotextile to go beneath rock armour as a heavy duty separation and filtration layer. The geotextile would form part of the necessary repair work to Network Rail Wales’ embankment at Old Colwyn, Conwy.

During the design phase, Atkins considered and appraised options using either 3,000kg or 6,000kg rock armour with an appropriate grade of MultiTrack™ SNW geotextile beneath. The final design solution was then agreed between Atkins, Alun Griffths (Contractors) Ltd and Wrekin Products, utilising 6,000kg rock armour overlying MultiTrack™ SNW140 geotextile.

Related case study

Holmwood Park TreeBunker tree pits

The Holmwood Park development of new homes in Ferndown, Dorset, has been created by Bellway Homes Ltd on a site surrounded by large green spaces including 1,000 acres of stunning parkland and forest.

The aim of the new residential development was to create an estate that offers residents a perfect blend of town and countryside living.

Bellway Homes

Bellway Homes

Read the full Case Study
Related case study

Ground stabilisation for Code Fitness Gym

We successfully implemented a ground stabilisation solution for Caliber Construction to complete the development of Code Fitness Gym in Nottinghamshire.

After encountering ground problems during the construction of a new gym on a countryside business park, Caliber Construction knew who to contact. However, contacting us after works had begun meant the need to provide a time effective solution was critical.

Code Fitness Gym

Code Fitness Gym

Read the full Case Study