Home
My Wrekin
Mostyn Sea Wall Repairs

Mostyn Sea Wall Repairs

  • Network Rail Wales

  • Mostyn, Flintshire

  • 10,000m MultiTrack

When gale force winds combined with high tides on Thursday 5th December 2013, the result was the worst storm surge to hit North Wales in years.

At Mostyn in Flintshire, where the Chester to Rhyl railway line runs along the sea front, the result was approximately 200m of the sea wall being breached in 6 separate locations, forcing the closure of the railway.

Network Rail engineers along with Alun Griffiths (Contractors) Ltd immediately started working around the clock using three heavy excavators to undertake the huge task of removing around 1,000 tonnes of the fallen sea wall from the railway. They replaced 150 tonnes of ballast, then repaired the track, signalling and other electrical equipment to allow the railway line to re-open.

This was achieved in the early hours of Tuesday 10th December when the focus moved to undertaking emergency repair work to the breaches in the sea wall before the next high tide on 2nd January 2014.

To ensure the sea wall repairs were completed as soon as possible, work continued around the clock and in between the high tides.

Mostyn, Flinthshire sea defence construction

The storm surge has caused significant damage to the railway in North Wales. We are doing everything we can to get passengers on the move again, but the scale of the work needed means it is likely to be several days before train services resume through the affected areas.

Mark Langman

Route Managing Director, Network Rail Wales

Mostyn, Flintshire sea defence construction

A solution devised jointly by Atkins, Alun Griffiths (Contractors) Limited and Wrekin Products was agreed. This consisted of sand bags wrapped in polythene, Wrekin MultiTrack™ SNW80 non woven geotextile and 2-4 tonne rock armour. The rock armour was placed to fill the breaches in the wall with the MultiTrack™ SNW80 beneath the rock thus forming a key part of the solution by acting as a heavy duty filter/separator.

Gallery

Related case study

Warner Brothers Studio

Wrekin helped Warner Brothers Studio and earthworks contractor Spadeoak to build new car parking areas as the land where they had previously built car parking on was being reclaimed for new buildings. Wrekin’s MultiTrack 1000 non woven geotextile was laid on the formation to provide separation and filtration.

Warner Brothers Studio
Warner Brothers Studio
Read the full Case Study
Related case study

Belton House Overspill Car Park

Built in the 1680s, the National Trust’s owned Belton House sits within 1300 acres of rolling deer park. The formal Dutch and Italian gardens are a major attraction for visitors to this quintessential country house estate. The National Trust commissioned expansion of their car parking facilities. A 25,000m2 field within the property was identified to provide additional parking spaces during the peak visitor times during Spring and Summer.

National Trust
National Trust
Read the full Case Study