Home
My Wrekin
William Davis Homes, Oak Grange Development

Value Engineed Road for Oak Grange housing development

  • William Davis Homes

  • 40m adoptable road

The Wrekin Products geogrids team value-engineered a fit-for-purpose adoptable road for a new Derby housing development, working with the city council, William Davis Homes and S&L Groundworks.

The team created an adoptable road solution for new housing development Oak Grange. Derby City Council’s overseeing engineer had previously highlighted various issues surrounding the creation of a permanent adoptable road that needed to be resolved before the adoption could progress.

The Wrekin team visited the site and identified that, before using a geogrid solution to significantly reduce the road foundation thickness, a performance trial was needed to prove efficacy for implementation. This was due to the very weak subgrade and the potential for differential movement.

First, Wrekin cleared a 20 metre long on-line area down to the sub-formation, with an additional ten metres at either end to allow for access and egress. An initial layer of MultiTrack™ MT1000 geotextile membrane provided separation of fines and filtration of water flow, which could have otherwise weakened the foundation over time.

While the geotextile membrane provides effective separation and filtration, the subsequent geogrid layer(s) provide efficient stabilisation through robust reinforcement of the 6F5 aggregate (capping materials).

MultiTrack with sub-base and E'Grid
Shahid Raza BEng(Hons) CEng MICE - Engineering Manager‑ UK and Ireland

A further granular sub-base layer was installed and tested, producing results between 70% and 100%, far exceeding the requirement of the pavement foundation. This confirmed that the geogrid solution and application was suitable for adoption to overcome the identified problems.

Shahid Raza, BEng(Hons) CEng MICE

Wrekin Products Ltd.

Oak Grange housing development by William Davis homes

The first layer of Wrekin’s E’GRID™ rigid biaxial geogrid was rolled out over the top of the MT1000. 250mm of 6F5 aggregate was placed and then compacted by a roller, followed by another layer of geogrid and a further 250mm of 6F5.

The substantial half metre reduction in foundation thickness over a conventional founding section reduced the total excavation and export of earthworks, therefore reducing the overall import and compaction of aggregates required.

After construction of the founding layers, plate bearing tests confirmed the in-situ performance at the formation level, on top of geogrid stabilised capping layers. Five plate bearing tests were taken on the inner 20 metres of the performance trial area, with the highest result being 47% and the lowest result being 18.7%. The performance trial area therefore exceeded the preliminary requirement of 15% at formation level.

A further granular sub-base layer was installed and tested, producing results between 70% and 100%, far exceeding the requirement of the pavement foundation. This confirmed that the geogrid solution and application was suitable for adoption to overcome the identified problems.

Altogether, this project demonstrates how value engineering solutions such as geogrids can be used to solve general and site-specific issues for the housing sector, while simultaneously saving contractors time and money.

Gallery

Related case studies

Case study

Supporting the Scottish National Gallery Revamp

We supported a hugely prestigious, multi-million-pound transformation project at the Scottish National Gallery in Edinburgh. The gallery in the heart of a World Heritage site, has been the scene of an ongoing major revamp. We were asked to provide technical advice on dealing with the topsoil erosion control needed as part of new landscaping and paths in the gallery’s grounds.

AHF Construction Management
AHF Construction Management
Read the full Case Study
Case study

Longhill burn Wind Farm

A new multi-million-pound wind farm is currently being constructed in West Lothian and, upon completion in 2022, it will be one of the largest onshore farms in the UK. Work at Longhill Burn wind farm in West Calder started in April 2021, with operations and management delivered by leading wind farm business, Energiekontor UK.  

A E Yates
A E Yates
Read the full Case Study